Really poor at Customer Service. Chose a condo in Building One at Lake House in Grimsby. We were not offered a choice in Building Two, as this was to be a later construction.
That was September 2015.
We were given a movie-in date of September 298, 2017; today we hear that we will be unable to move until February 2018.
This is an unreasonable delay, our house is sold, we have arrangements to stay until December 2017, now we have an additional three months cost of accommodation and storage - where will this money come from?
The buildings looked to be in a fairly complete state of construction in April 2017.